I don't understand why at 17:00h my Schedule Agreements update automatically:
- Cumulative Issued Quantity and Cumulative Delivered Quantity.
System only updates all schedule agreements that have a delivery with delivery date for this day. And at 17h theses quantities are update with the total quantity and not for the total of the last year.
This is very important for us because ou logistics department has to update between 5 to 10 SAs for this issue.
I appreciate your help to:
- Understand why this is updated
- know customizing point to configure this "updating" (I don't want to update automatically. I only want to update manually with a delivery correction)
- know a program (is this is not standard) where I can define a logic to control that issue.
I hope to be clear in my comments.
Thanks in advance for you help.