Hi,
My client has 2 construction projects. Only one labor activity type, One Work center.
Planned labor rate for current month is previous month actual labor rate.
Requirement is calculate the Actual activity rate, reevaluate the Projects with actual labor rate end of the period.
I Proposed but Clients doesn't want this scenario: Create one Project cost center, post the Salaries by Payroll then calculates actual Labor rate (Actual labor cost / Projects actual labor hours) then reevaluate the Projects with actual labor rate end of the period.
Clients was asking Create 2 Cost centers (Project 1 and Project 2)
Assign cost centers in employee master respective project wise.
Labor cost (Salaries) updates Project 1 and Project 2 cost centers by Payroll.
Then calculate project wise labor per hour rate and reevaluate Projects with respective project actual labor rate.
Project 1 Labor cost / Project 1 Actual labor hours = Project 1 Labor Per hour rate.
Project 2 Labor cost / Project 2 Actual labor hours = Project 2 Labor Per hour rate.
My question is If i create 2 cost centers Project 1 and Project 2 but i can only assign one cost center to work center (PS consultant confirmed only one work center is there).
Please suggest me good solution.