Issue with Commitment posting to WBS while Creating Material PR/PO

$
0
0

Hello,

 

We are facing issue, Commitment is not posting to WBS while creating PR/PO from PS and MM both module. But if we create Service PR/PO all postings of Commitment done as per standards.

 

I have Checked the PS config, OBYC settings and G/L Settings, all are fine and unchanged. Only thing what we did is config for MRP. Later MRP as requirement changed we reversed all config done for MRP.

 

Does MRP settings are the base for this issue? I am not sure where did i went wrong, Please Help me.

 

Regards,

Omkar Deshpande