Hi All,
Can anyone tell me what is the exact use of 'release stop indicator' function in milestone. For example, I have created 4 Activity:
- Activity 1 Relation FS
- Activity 2 Relation FS
- Activity 3 Relation FS
- Activity 4 Relation FS
So after 2nd activity I put milestone 'release stop indicator' and when I'm going to release all activity by releasing network. 1st and 2nd activity is released after that I got I 'release stop indicator message' and my 3rd and 4th activity also released which should not be released as I already put 'release stop indicator' milestone on 3rd actvity so system should releasing all activity after 3rd acivity.
So kindly tell me how I resolve this issue.
Regards,